The week of July 11, 2022, the electrical work necessary for the reconfiguration of Simcox Hall was accomplished.
July 19, 2022: Simcox Hall prepared for the installation of dry wall.
July 20, 2022: Installation of the dry wall.
July 21, 2022: Application of dry wall compound begins.
July 22, 2022: All the dry wall compound is properly applied.
July 25, 2022: Dry wall compound was sanded and walls are now ready for primer and paint. Also the heating and air-conditioning duct-work was reconfigured for the new layout of Simcox Hall.