On Monday, June 27, the work began to reconfigure Simcox Hall, our classroom wing, into two full-sized elementary school classrooms. Below are pictures of this week’s progress.

Sunday, June 26: The building is fully emptied in order for the work to begin.

Monday, June 27: Demolition begins.

Tuesday, June 28: Demolition continues.

Wednesday, June 29: New center wall is installed.

Thursday, June 30: New east end doorways framed and more demolition.