We found out last week that the roofing material to match our existing roof must be special ordered and the roofer who will install it cannot be here until the middle of July (about 3 weeks from now). Always something to slow us down! A tarp was installed over the building today to help keep our summer afternoon rains out of the building. The plumber was here today to install the lines for the bathroom in the addition. We also got an update today on our bell tower. It appears that the primary fabrication work in nearly complete on our tower up at Dave Steel Company in Asheville. Delivery is expected at the end of July.